After the post report a minimum of 10 days, the project room or board room was assigned to start issuing bid. Bid can play for free or for sale (but not to exceed 2 million for procurement cases in the country).After the time for the contractor to prepare tenders (minimum 15 days for procurement in the water, 30 days for international bidding), the project started to receive tenders. Small package of own time preparing tenders to a minimum 7 days).Time base and locations outlined in the tender notice, the contractor provides lodging tenders in accordance with the regulations. After receiving the status quo the tenders submitted on time and is managed by records management mode "Suite" the opening of bids was conducted publicly soon, have the witness of the contractors and representatives of the company. The main point of tenders must be members of the expert review the full record bid in the closing minutes of opening the tenders according to form BM/DA-05-08