The negotiated contracts are not changing the unit price bid by the contractor after the fixes, false and edit value minus a discount (if any). In the process of evaluating tenders and negotiated the contract, if the volume of tenders stated in the table of the prognosis of bidder lacking compared to the profile design, the tender side required the contractor to supplement the lack of workload on the basis of the unit price was welcome; in case the tender has not yet had the unit price, the bid side owner reviewing reports, decided the price stated in the approved estimates for the lack of workload compared with the profile design or the price of the other bidders have passed technical assessment step if this unit price is lower than the price approved in the estimation of package;