Below are the results for the calculation of traffic at building CJ Building with 6 scenarios. Only the sixth scenario is acceptable, while the other scenario shows the building's capacity more than the overall haul of 4 lifts. However, to improve in comparison with the current situation, the results show: tags 2 Elevator C & D not down to the basement on peak hours will significantly improve. To do this, on the Schindler has 1 solution is to use the Lobby elevator key from time to time to the Vision are pre-installed and can be edited. The cost for the building's elevator 5 is 480 million (not including VAT) Compared with the results of the 2009 analysis from Jardine Schindler Hong Kong, the above solution is also recommended