Below are the results for the calculation of traffic in and out at the building CJ with 6 scenarios. The sixth scenario is only tentative, and the other scenario showed overall haul of 4 elevators, not enough to meet visitors in the building.So, to improve the current situation, the results show: tags 2 Elevator C & D not down to the basement on peak hours will significantly improve. To do this, Schindler has 1 solution is to use "Lobby Vision" to lock the elevator from time to time are pre-installed and can be edited. The cost for the building's elevator 5 is 480 million (not including VAT) Compared with the results of the 2009 analysis from Jardine Schindler Hong Kong, the above solution is also recommended