The major project milestonesMay 10-7: complete the production of submarine cablesMay 23-8: cable reception Ceremony at Dung quat portSeptember 26-8: cable Laying the district coast of Binh sonAugust 8-9: complete connection cables to the shores of the island of Ly sonNovember 15th-9: close the technical power of successAugust 28-9: official operation.