Dear All,
Since yesterday 19.12.2016 Sawmill / Finger Jointing Line production processing is not in operation Due to EVN / MFJSC main power problem.
The SM / FJ thể là lines still work at the Boiler / KD and wood putty sticks sorting and FJLB board repair and grading thanks to the # 8 Substation Genset operation using diesel oil fuel in ..
But today at 10:00 am at complete shutdown SM / FJ lines Due to # 8 Substation Due to Diesel Genset stopped operating fuel oil shortage.
Diesel fuel Material request was made on 12 Dec.2016 but so far not yet delivered. Based on site purchasing person, as per có follow up to Ms Huong / Ms Dinh, payment of said material not yet done as of this morning.
For your information.